SEL에서 권장하는 프로젝트 모니터링 지표


 

MEASURES CLASS MEASURE SOURCE FREQUENCY MAJOR APPLICATION
ESTIMATES Estimates of:
•Total SLOC (new, modified, reused)
• Total units
• Total effort
• Major dates
Managers Monthly • Project stability
• Planning aid
RESOURCES • Staff hours (total & by activity) Developers Weekly • Project stability
• Replanning indicator
• Effectiveness/impact of the development process being applied
• Computer use Automated tool Weekly
STATUS • Requirements (growth, TBDs,
changes, Q&As)
Managers Biweekly • Project progress
• Adherence to defined process
• Stability and quality of requirements
• Units designed, coded, tested Developers Biweekly
• SLOC (cumulative) Automated
tool
Weekly
• Tests (complete, passed) Developers Biweekly
ERRORS/
CHANGES
• Errors (by category) Developers By event • Effectiveness/impact of the development process
• Adherence to defined process
• Changes (by category) Developers By event
• Changes (to source) Automated tool Weekly
FINAL
CLOSE-OUT
Actuals at completion:
• Effort
• Size (SLOC, units)
• Source characteristics
• Major dates
Managers 1 time at completion • Build predictive models
• Plan/manage new projects
Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s